1 year, 8 months ago Ian Gilfillan

It's difficult to tell at this point. The 10.11 alpha is scheduled for mid-September, and you can get a rough idea of when a GA release could be by looking at the progress of previous releases, for example 10.7, which moved from alpha in September to GA in February. Treat this as no more than optimistic estimate, as there may be delays and intermediate releases if more issues are found.

 
1 year, 8 months ago Dave Martin

Completely understand, thank you. Just looking for ammo to justify why we're using what may be an out of support release when the time comes. Looking forward to10.11.

 